The City of Woodstock is continuing to enhance its aging infrastructure through its Gould Street Water Main Replacement project. Once complete, the project will have replaced and upsized a quarter mile of water main from 4” to 8”, which reinforces the system's operation and longevity. Various storm and sanitary sewer point repairs were also completed to ensure all underground improvements within the roadway were completed before resurfacing and reconstruction of the various roadways.
 

The Janak and Weck subdivisions, located in the Village of Algonquin, are older subdivisions within the municipality. The Village is looking to provide residents with long-term sustainable solutions to update its existing aging water and sewer infrastructure.                                                                                     To achieve this goal, the Trotter team is preparing a feasibility study that outlines the best options for improving the infrastructure in these subdivisions. One of the main components will be assessing whether to rehabilitate the existing rear-yard sanitary sewers or to replace the sewers within the right-of-way in front of the properties.                                                                                     Once the study is completed, the Village will have the data needed to make an informed decision that results in the most cost-effective, sustainable infrastructure plan for this area.                                                                   
 

Trotter and Associates, Inc. (TAI) continues its partnership with the DuPage County Department of Stormwater Management on the rehabilitation of the West Lobe Pump Station at the Elmhurst Quarry Flood Control Facility. This critical infrastructure serves as a flood control system by storing excess flow during major rain events and later pumping stormwater back to Salt Creek once conditions recede.                                                                                                                                     Independent Mechanical Industries, Inc., and their subcontractors are on schedule for the West Lobe Pump Station to be returned to service this fall. Over the last several months, the team completed installation of four 500-hp pumps and rehabilitation of the discharge piping supports along the 100-foot quarry highwall. Additionally, the pump station’s electrical system was upgraded with a 2,500-amp switchboard and VFDs to provide a long-term reliable electrical system for the facility.
 

In 2022, Trotter and Associates, Inc. completed an assessment of the Village of Algonquin’s Braewood Lift Station. The primary improvements focused on increasing the station’s capacity to handle the rapid growth in both the Braewood Lift Station service area and the upstream Grand Reserve Lift Station service area.                                                                                     With the increased capacity of the station, the velocity through the existing 10-inch force main exceeded allowable limits. To address this, a 16-inch force main was included in the design, which was constructed in 2024.                                                                                                                                     With the force main constructed, the station rehabilitation has commenced. Work within the station includes upsizing the piping and pumps, replacing the grinder, and improving both the electrical and HVAC systems. Upon completion of the work, the pumping capacity of the station will be increased from 1,500 gallons per minute (GPM) to 5,000 GPM, allowing the Village to meet both current and future development demands.
 

Trotter and Associates, Inc. recently completed a Wastewater Treatment Plant Consolidation Study for the Village of Addison. As a result of the study, the Village elected to fully consolidate their facilities in lieu of doing a partial consolidation or rehabilitating and upgrading their existing treatment facilities.                                                                                                            For constructability and financing advantages, the consolidation was separated into three phases. The Trotter team has begun developing the improvements for the first phase, which includes upgrading and expanding the North Wastewater Treatment Plant. Upon completing all three phases, this facility will process all wastewater flows from within the Village.                                                                                                            Phase one includes construction of a 44,500 square foot Garage/Laboratory/Operations Building, Screening Building, Advanced Treatment Building (low-P treatment basins, tertiary filters, and UV disinfection), and excess flow clarifiers.                                                                                                            In addition to these new structures, the following existing processes will be improved: upgrades to the grit removal system, rehabilitation of the primary and final clarifiers, rehabilitation and expansion of the aerobic digestion process and digester gas storage, and expansion of the biological process, which includes conversion from a two-stage extended aeration process to a single-stage A2O process. Construction is planned to begin in 2026 and continue into 2030.
 

Previously, Trotter and Associates completed a Wastewater Facility Master Plan for the Village of Roselle’s Joseph L Devlin Wastewater Treatment Facility. The plan identified four essential projects: Plant Expansion and Phosphate Removal, Grit Removal Rehabilitation, Secondary Clarifier Replacement, and UV Disinfection Conversion.                                                                                                            Each project identified above is interrelated and will allow the facility to meet new regulations, support Village growth, and upgrade aging infrastructure. To provide the village with the best financial and operational benefit, these projects were combined into one WWTF Plant Expansion and Nutrient Removal Upgrades project.                                                                                                                         With preliminary engineering complete, the Trotter team is working on the final design documents for the project. This phase is expected to be wrapped up in the first quarter of 2026, with bidding and construction to follow.                                                                               
 

